POST BID - GJRC GROUP HOME A/C

Location:      577 -29 1/4 Road, Grand Junction Co 81504     

Accepting Proposals by Email:     No later than Monday January 6, 2020 at 2:00 PM

RFI's:      Are to be submitted by email no later than Friday December 6, 2019 at 3:00 PM

Project Scope:      Replace A/C infrastructure that has outlived its useful life in nine (9) group homes that are associated with the Grand Junction Regional Center.        

Taxes:     The project is tax exempt.  Please do not include taxes in your proposal.

Project Schedule of Dates:
  • Pre-Submittal Question Deadline: Friday, December 6th, 2019 at 3:00 PM
  • Deadline for Proposal Submittal: Monday January 6th, 2020 at 2:00 PM
  • Anticipated Construction Duration: February 24th, 2020 - December 31st, 2020  

If you have any questions or comments feel free to contact me at (970) 245-9343.  Thank you.


Ryan Peskuski, Estimator
Ford Construction Company, Inc.
estimating@fordconstruction.org

DOCUMENTS