POST BID - CMC Nursing Simulation Lab

ADDENDUMS POSTED BELOW.  BID DATE HAS CHANGED

Project:
           CMC Nursing Simulation Lab
 
Location:        3000 County Rd 114, Glenwood Springs Colorado
 
Accepting proposals by Email:        No Later than 5:00 pm Monday Nov 8, 2021. 
Ford’s formal bid is due to the client Tuesday November 9th.  Subcontractor and vendor pricing is requested the Monday prior to review and call to discuss if we have questions.
 
RFI’s:             Are to be submitted by email no later than 10:00 am Friday Oct 15th 2021 
 
Project Scope:           Interior renovation of approx. 5,650 SF in the Spring Valley Student Center.  Work includes, demo, cast-in-place concrete, fabricated metals, rough carpentry, P-Lam cabinets, firestopping, acoustical joint sealants, HM doors/frames, wood doors, door hardware, glazing, light gage framing, drywall, ACT, resilient flooring, carpet tile, wall coverings, painting, specialties, projection screens, roller window shades, fire suppression/wet pipe, plumbing, mechanical, electrical, fire alarm and low voltage.
 
Bid Form:      The client, CMC has provided a required bid form.  Please breakout your proposal in accordance with the bid form.
 
Taxes:             The project is tax exempt.  Please do not include material taxes in your proposal.
 
Project Schedule:
  • Pre-Submittal Question Deadline:      10:00 am Friday Oct 15th, 2021
  • Deadline for Proposal Submittal:       5:00 pm Monday Nov 8th, 2021
  • Anticipated Construction Duration:   January 2022-April 2022